| #Q001 | administrative | unknown | mandatory | Project Assessment Responsibility | other | The listed authorities are responsible for the project assessment. | | medium |
| #Q002 | design | treatment | mandatory | Detailed Design Development | wastewater | Aski will develop a detailed design of the engineered wetlands area in association with Native Plant Solutions (plant specialist consultant). | Project involves constructing an engineered wetland incorporating phytoremediation for an inoperable leachate collection system. | medium |
| #Q003 | design | treatment | mandatory | Wetland Construction and Monitoring Procedures | wastewater | Construction of the wetlands, approximately 1.5 hectares in area, will include earthwork (cut/fill procedures) along the base of the former borrow pit and drainage area, berm construction along the south limit, realignment of existing drainage with flow controls, enhancement of native species vegetation (cattails or Typha latifolia) for wetland establishment, followed by monitoring. | | medium |