| Req ID | Category | Intent | Legal Status | Name | Subdomain(s) | Context | Conditions | Confidence |
|---|---|---|---|---|---|---|---|---|
| #Q001 | design | operational | mandatory | Forested Buffers Maintenance | wastewater | Forested buffers will be maintained around the property edges where possible. | where possible | high |
| #Q002 | administrative | unknown | mandatory | Lagoon Expansion Approval | wastewater | Expansion of the existing lagoon requires approval from the Government of Manitoba under applicable acts and regulations. | high | |
| #Q003 | administrative | operational | mandatory | Lagoon Operating Licence | wastewater | The existing lagoon is currently operating under an existing Environment Act licence and will continue to operate under the same licence following expansion. | following expansion | high |
| #Q004 | design | treatment | mandatory | Water Treatment Plant Upgrades | drinking water | The WTP be upgraded to include mechanical, treatment process, and electrical components, and a new standby generator and two new raw water wells will be added. | high | |
| #Q005 | design | operational | mandatory | Clay Sourcing Location | wastewater | Clay for the lagoon cell liner will be sourced from a borrow pit located approximately 3.5 km north of the existing lagoon. | high |
| Req ID | Category | Intent | Legal Status | Name | Subdomain(s) | Limit Type | Limit Value | Context | Conditions | Confidence |
|---|---|---|---|---|---|---|---|---|---|---|
| #R001 | design | operational | mandatory | Design Population Horizon | wastewater | requirement | 20 years | Requirement for the design population capacity of the community of Sturgeon Landing | high | |
| #R002 | design | treatment | mandatory | Lagoon Cell Count | wastewater | requirement | 2 cells | Expansion of the facultative lagoon system | high | |
| #R003 | design | treatment | mandatory | Lagoon Expansion Area | wastewater | requirement | 7 hectares | Approximately 7 hectares of land for the two-cell facultative lagoon expansion | high | |
| #R004 | design | operational | mandatory | New Raw Water Wells | drinking water | requirement | 2 wells | Addition of new raw water wells to the current water treatment plant (WTP) | high | |
| #R005 | design | operational | mandatory | New Standby Generator Count | drinking water | requirement | 1 generator | A new standby generator is to be added as part of the mechanical, treatment, and electrical upgrades to the WTP. | high |
No definitions.