| Req ID | Category | Intent | Legal Status | Name | Subdomain(s) | Context | Conditions | Confidence |
|---|---|---|---|---|---|---|---|---|
| #Q001 | administrative | unknown | mandatory | Project Assessment Responsibility | wastewater | The listed authorities are responsible for the project assessment. | Applies to this non-designated project on federal lands or outside Canada. | high |
| #Q002 | operational | treatment | mandatory | Septic System Replacement Requirement | wastewater | The existing septic disposal system at Loggiecroft wharf needs to be replaced. | Specific to the Loggiecroft wharf site | high |
| #Q003 | design | operational | mandatory | System Footprint Constraint | wastewater | The new system may be pushed slightly to the east, but will remain largely within the existing footprint. | Applies to the installation of the new replacement system | high |
No quantitative requirements.
No definitions.