| #Q001 | operational | operational | mandatory | Clearing and Grubbing Timing Constraint | wastewater | Clearing and grubbing of the site at all SPS locations will take place outside of the migratory bird nesting season. | At all SPS locations | high |
| #Q002 | operational | operational | mandatory | Topsoil Retention Procedure | wastewater | Topsoil will be retained, unmixed, near the site from which it was removed. | | high |
| #Q003 | operational | operational | mandatory | Demolition and Salvage Specifications | wastewater | The existing fence will be removed and the entire existing structure will be selectively demolished and salvaged except for the wet well at each SPS location. | At each SPS location | high |
| #Q004 | design | operational | mandatory | SPS Superstructure Construction | wastewater | A new, expanded SPS superstructure composed of electrical room, generator room and pump room as required at each site will be constructed. | At each site | high |
| #Q005 | design | operational | mandatory | Site Regrading and Stormwater Drainage | wastewater | The SPS sites will be regraded so that stormwater drains freely away from the proposed buildings and to limit flooding from runoff flows caused by rainfall events or snow melt. | | high |
| #Q006 | design | unknown | mandatory | Imported Soil Quality | wastewater | All imported soil materials will be clean and free of hazardous materials. | Applies to imported soil materials | high |
| #Q007 | design | operational | mandatory | Security Fence Specifications | wastewater | A new maintenance-free, industrial grade security fence (min overall height of 1.83m) will be installed around each site and will include a vehicle access swing gate and a pedestrian door entrance, both with locks. | Around each site | high |
| #Q008 | design | operational | mandatory | Back-up Power System Requirement | wastewater | Back up power systems is also included in the upgraded design. | | high |