| Req ID | Category | Intent | Legal Status | Name | Subdomain(s) | Context | Conditions | Confidence |
|---|---|---|---|---|---|---|---|---|
| #Q001 | administrative | unknown | mandatory | Project Assessment Responsibility | other | The listed authorities are responsible for the project assessment. | This is a non-designated project on federal lands or outside Canada. | high |
| #Q002 | design | operational | mandatory | Scope of Works for Permit Extension | wastewater | The scope of works that remain to be completed includes: * The installation of pre-cast concrete covers over the duckbill valves on the diffuser manifold * Placement of the backfill material and rip rap over the diffuser manifold * Removal of the temporary bulkheads that are in the riser pipe assembly | Completion of the approved project permit PER 17-093 extension. | medium |
No quantitative requirements.
No definitions.